Campaign Library
What is this initiative?
The Campaign Library initiative is a funded piece of work that will allow Mautic users and administrators to export and import campaigns from one Mautic instance to another. It’s planned that the ability to do this will allow the development of a full set of ‘portable’ campaigns that all Mautic users can share with each other, much like plugins.
This initiative will:
Save users time when setting up campaigns
Promote best practice adoption among marketers to get the best out of Mautic
Enhance Mautic’s flexibility and usability, especially where users access Mautic across many instances
Who is funding the initiative?
The project is being funded by NLNet as a part of their NGI Zero Commons fund. There were two phases to the project, Phase 1 and Phase 2.
Phase 1: See more info on the Community Blog.
Phase 2: See more info on the Community Blog.
Where does this initiative fit within Mautic’s roadmap?
Campaign Library Phase 1 is released in Mautic 7.0.
Campaign Library Phase 2 is scheduled for release in Mautic 8.0.
More on Mautic’s release strategy.
Who is in the team?
Name | Role |
|---|---|
Project Lead | |
Project Manager Phase 1 | |
Levente Bajusz | Developer Phase 1 |
Kaviyaa Devi | Project Manager Phase 2 |
| Developer Phase 2 |
Joey Keller & Rahul Shinde | Product |
John Linhart | Tech lead |
Ayu Adiati and Favour Chibueze | Documentation |
TBC | Marketing |
TBC | Community |
What’s the project plan?
Phase 1
Dates | Task | Outcome |
|---|---|---|
Mon 13 Jan - Fri 24 Jan | Clear understanding of what the project needs, scope and risks Planning of the forthcoming sprints Basic proof of concept | |
Mon 27 Jan - Fri 21 Mar | Sprints 1-4 | 1st half of development |
Mon 24 Mar - Fri 16 May | Sprints 5-8 | 2nd half of development |
| Sprint 9 & 10 | Testing, refinement and quality assurance |
Mautic 7.0 release dates | 24 Feb 07.0-alpha |
|
Phase 2
Dates | Task | Outcome |
|---|---|---|
| Clear understanding of what the project needs, scope and risks Planning of the forthcoming sprints Basic proof of concept | |
| Sprints 1-4 | 1st half of development |
| Sprints 5-8 | 2nd half of development |
| Sprint 9 & 10 | Testing, refinement and quality assurance |
Mautic 8.0 release dates | 8.0 alpha - Q3 2026 8.0 beta - Q4 2026 8.0 release candidate - Q1 2027 8.0 General Availability - Q2 2027 |
|